Progress of VEGA project March
2007
March 2007
Funding results for 2007:
27K€ INSU + PNPS + ASHRA
13K€ OCA + Gemini
Pending CNRS + PPF (coming soon)
Spectograph realignment after re-coating
CSM first mounting & test before anodization.
This device is manufactured in OCA Calern workshop by C Munier,
R Brunet, X Martin

The periscop mechanical design realized by Laszlo Strumann of Chara
team is completed
and ready for manufacturing. On these views you could see some red
devices which are pico-motors to
adjust the mirror orientation
A view with mirror in upper position where beams could continue to
Chara Sources device.

A view with mirror in down
position where beams are directed to Vega instrument

Cleaning &
re-coating spectrograph optical element in Nice Observatory optical lab
The vacuum tank in the clean area

Inside the vacuum tank during evaporation

Vega mirror during evaporation
through the vacuum plant window

|
|